VoiceLogPro › Lien Deadlines › Florida
The three deadlines every Florida subcontractor must track — preliminary notice, lien filing, and enforcement. Values below are reproduced from our verified 50-state reference; confirm with a Florida construction attorney.
| State | Florida |
|---|---|
| Preliminary Notice? | Yes |
| Deadline | 45 days from first furnishing (Notice to Owner) |
| Notes |
| State | Florida |
|---|---|
| Lien Filing Deadline | 90 days from last furnishing |
| State | Florida |
|---|---|
| Lien Enforcement Deadline | 1 year after filing |
A lien timeline is not one date. It is a sequence of separate steps. For Florida, start by identifying whether the preliminary-notice rule applies to your role and project. The reference above records that requirement as Yes and gives the deadline as 45 days from first furnishing (Notice to Owner). Do not substitute the date of an invoice, payment application, or internal reminder unless the statute makes that event the trigger.
The filing window is a different step. The source data states 90 days from last furnishing. The enforcement window starts after a lien has been filed. For Florida, that period is 1 year after filing. Keeping these events separate helps prevent a notice deadline from being mistaken for a filing deadline.
Suppose a subcontractor is reviewing an unpaid project. This example does not invent calendar dates. It shows which project records must be matched to each sourced rule before a calendar date is calculated.
The result is an auditable chain: the project event, the applicable rule, the calculated deadline, and the document that proves when each event occurred. VoiceLogPro can preserve daily work records, but it does not decide whether a statutory exception applies. A licensed Florida construction attorney should confirm the final dates before anyone relies on them.
Keep the contract, notices, proof of service, daily logs, delivery records, change orders, completion records, the recorded lien, and court or filing receipts together. Label the first furnishing, last furnishing, completion, notice, filing, and enforcement events plainly. If two records conflict, flag the conflict rather than silently choosing the date that leaves more time.
This page cites Fla. Stat. ch. 713. Read the official text for definitions, claimant-specific rules, service requirements, exceptions, and any event that can shorten a period. The table is a planning reference, not a substitute for the statute or legal advice.
See all states in the 50-state lien deadline cheat sheet. Nearby: Alabama · Alaska · Arizona · Arkansas · California · Colorado · Connecticut · Delaware.
📬 Email me Florida's deadline dates + the free Defense Kit
Your dates and a free daily-report Defense Kit, sent to your inbox. No spam, unsubscribe anytime.
This is general information, not legal advice. Lien laws change and vary by project type. Verify every deadline with a licensed construction attorney in your state before relying on it. Data current as of 2026-08-14. Statute: Fla. Stat. ch. 713 — official text. Compiled reference: VoiceLogPro 50-state lien deadline reference · Download data (CC BY 4.0)